Warning Referenced Activities

Type

Selection

Range

The settings listed below

Default

Common_warning_default

When an activity is referenced in one of the sequencing attributes of a sequential resource or in one of the level modification attributes of a parallel resource, but is not referenced in the attribute “activities” of that resource, AIMMS will issue a warning. Consider the following example:

Set mySet {
    Index: i, j, k;
    Definition: data { a, b, c, d, e, f, g, h, i, j, k };
}

Resource res {
    Usage: sequential;
    ScheduleDomain: Timeline;
    Activities: act(i):ord(i)<5;
    ComesBefore: (act('f'),act('g'));
}

AIMMS will issue the warning message:

The activity act('f') referenced in the attribute "comes before" of resource res, is not scheduled on that resource.

The option Warning_Referenced_Activities determines how activities referenced in a sequencing or level modification attribute, but not in the activities attribute, are reported, depending on the following settings:

  • Off

Do not issue a warning.

  • Warning_collect

Issue a warning and post it to the global error and warning collector.

  • Common_warning_default

Take action depending on the option ‘Common warning default’.

  • Warning_handle

Issue a warning and post it to the nearest error handler.

  • Strict_warning_default

Take action depending on the option ‘Strict warning default’.

  • Error

Issue an error.

  • Error_in_develop_else_warning

In a developer system same as Error, in a deployment system same as Warning_handle

  • Error_in_develop_else_off

In a developer system same as Error, in a deployment system same as Off

  • Warning_in_develop_else_off

In a developer system same as Warning_handle, in a deployment system same as Off

Note

  • With the option Maximal Number of Warnings Reported you can set the maximal number of warnings that are shown in errors/warnings and message window.